| Event |
Date |
| Request for Proposal (RFP) issue date |
September 14, 2009 |
| Pre-Bid meetings and discussions start date |
October 6, 2009 |
Pre-Bid meetings and discussions end date |
October 16, 2009 |
Offers submittal closing date |
Extended to
October 23, 2009 |
Offers evaluation end date |
November 1, 2009 |
Contract award date |
November 5, 2009 |
Performance Bond Submittal deadline |
November 8, 2009 |
Final Contractor Team-1 selection date |
November 16, 2009 |
Final Contractor Team-2 selection date |
November 30, 2009 |
Final date for submittal by Contractor of the required insurances and any other pending item. |
January 26, 2010 |
Contract Start Work Date |
February 1, 2010 |
Team-1 Probation Period start date |
February 1, 2010 |
Team-2 Probation Period start date |
March 1, 2010 |
Partial handover from previous Contractor to new Contractor Team-1. |
March 31, 2010 |
Full handover from previous Contractor to new Contractor. |
April 30, 2010 |
Team-1 Probation Period end date |
April 30, 2010 |
Team-2 Probation Period end date |
May 31, 2010 |