Irani Oxy Engineering Complex |
|
|
 
* Designer & Consultant are “Nabil Gholam Architecture and Planning” (NGAP).
Project is designed to comply with a Certification Level according to the U.S. Green
Building Council's Leadership in Energy & Environmental Design (LEED) Rating System.
* Currently ongoing works are: Concrete pouring along foundation & vertical elements all along site, Slab on grade pouring in stages, Shuttering for first part of slab B1.
* Project start 3 October 2011 & completion date 7 October 2013, covering 735 calendar days.

|
|
|